Past Year QuestionsJIPMATQATime & Work

JIPMAT Time & Work — PYPs

1 solved Time & Work previous year question (PYQ) from JIPMAT past year papers — attempt each and check the answer.

Free SolutionsNo Login1 Questions
Q1:jipmat 2025QATime & WorkMediumQA · MCQ
40 men can complete a work in 48 days. 64 men started and did the same work for x days. After x days, 32 men increased, so, the remaining work is completed in 162316\frac{2}{3} days, then the value of x is
  • A5
  • B8
  • C10
  • D6
Pick an option to attempt
The Setup: We are measuring this task in 'man-days' (the amount of grinding one guy does in one day). The total work is a fixed pool of points, and we just need to track who did how much. Step 1: Calculate the total work pool. Total Work=40 men×48 days=1920 man-days\text{Total Work}=40\text{ men} \times 48\text{ days}=1920\text{ man-days} Step 2: Track the grinding phases. Phase 1: 64 men64\text{ men} work for x daysx\text{ days}. Work done in Phase 1 =64x=64x. Phase 2: The squad increases by 3232 men (64+32=96 men64+32=96\text{ men}). They grind for 162316\frac{2}{3} days. Convert 162316\frac{2}{3} to an improper fraction: 503\frac{50}{3}. Work done in Phase 2 =96×503=96 \times \frac{50}{3}. 96÷3=3296 \div 3=32, so Phase 2 work =32×50=1600 man-days=32 \times 50=1600\text{ man-days}. Step 3: Set up the master equation. Total work must equal the sum of both phases. 64x+1600=192064x+1600=1920 64x=1920160064x=1920-1600 64x=32064x=320 x=32064=5x=\frac{320}{64}=5 Final Answer: 5

Browse other topics · JIPMAT