Q1:jipmat 2025QA › Time & WorkMediumQA · MCQ
40 men can complete a work in 48 days. 64 men started and did the same work for x days. After x days, 32 men increased, so, the remaining work is completed in days, then the value of x is
- A5
- B8
- C10
- D6
Pick an option to attempt
The Setup: We are measuring this task in 'man-days' (the amount of grinding one guy does in one day). The total work is a fixed pool of points, and we just need to track who did how much.
Step 1: Calculate the total work pool.
Step 2: Track the grinding phases.
Phase 1: work for .
Work done in Phase 1 .
Phase 2: The squad increases by men (). They grind for days.
Convert to an improper fraction: .
Work done in Phase 2 .
, so Phase 2 work .
Step 3: Set up the master equation. Total work must equal the sum of both phases.
Final Answer: 5